UWWTP : SI_AGG_RENČE_1518 - Identifier : SI_AGG_01518 - Status : Active - Not connected - Reporting year : 2016
Region (NUTS) Code : SI043 - Region (NUTS) Name : SI043

compliance Time Line
List of all the year available for the agglomeration

2012

2014

2016

 
Compliant
 
Not compliant
 
Not relevant
 
No information
 
?


Description
Load entering UWWTP (p.e.): 
load expressed in population equivalent shall be calculated on the basis of the maximum average weekly load entering the treatment plant during the year, excluding unusual situations such as those due to heavy rain (Article 4 of the Urban Waste Water Treatment Directive 91/271/CE)
Not available
Method used to determine the load : 
Not available
Rate of entering load transported to this UWWTP by trucks (%): 
Not available
Physical Capacity (p.e.): 
Not available
Waste water treated (m3/y): 
Volume of waste water treated and partially treated in the UWWTP
Method used to determine the volume of waste water treated: 
Not available
Treatment performance: BOD5: 
Biological Oxygen Demand
Not available
Treatment performance: COD: 
Chemical Oxygen Demand
Not available
Treatment performance: TSS: 
Total Suspended Solids
Not available
Treatment performance: Total nitrogen: 
Sum of total kjeldahl nitrogen (organic, ammonia and ammonium), nitrate and nitrite
Not available
Treatment performance: Total phosphorus: 
Sum of dissolved phosphorus and insoluble phosphorus
Not available
Treatment performance: Other: 
e.g. e-coli
Not available
Compliance: 
Not compliant
Treatment type in place: 
No information
Treatment required: 
Secondary treatment
Treatment met: 
No
Performance met: 
No
In cause of failure: Bad operating/Bad design or dimensioning: 
0
In cause of failure: Bad design or dimensioning: 
0
In cause of failure: Further information on cause of failure: 
Not available
See diagram

Load and concentration per parameter :

Incoming Discharged Rate
BOD 0 t/year 0 t/year
COD 0 t/year 0 t/year
Nitrogen 0 t/year 0 t/year
Phosphorus 0 t/year 0 t/year
* Concentration calculated using the annual load and the annual volume of wastewater treated.
Incoming and discharged loads (t/year)
See the data table
Graphical network summary
Network
Agglomerations : 1 Agglomeration : SI_RENČE_1518
(Generated
Network
Network
Entering :
0 p.e
Network
reseau
1 DCP(S)
Discharge point: SI_DP_SI_AGG_RENČE_1518
(NA)

    Main treatment :
  • Network : Compliant
  • Network : Not compliant
  • Network : No information / Not relevant
    More stringent treatment :
    Performance :
  • Network : Pass performance
  • Network : Fail performance
  • Network : Not relevant

    Type :
  • N : Nitrogen removal
  • P : Phosphorus removal
  • UV : UV treatment
  • MICRO : Micro Filtration

    Type :
  • CHLOR : Chlorination
  • OZONE : Ozonation
  • SAND : Sand filtration
  • O : Other more stringent
    Discharge point :
  • Network : Discharge point
  • DCP(S) : Discharge point(s)
Waste Water Network Connexions
Linked agglomeration(s): 
Linked receiving area(s): 
Not available
Linked discharge point(s): 
Site information
Characteristics
 45.88413444
 13.67370294
Date of closing: 

Not provided

Explanation for closing: 

Not provided

ID of the successor: 

Not provided

Primary treatment: 
No
Secondary treatment: 
No
N removal: 
No
P removal: 
No
UV: 
No
Ozonation: 
No
Sand filtration: 
No
Chlorination: 
No
Micro filtration: 
No
Other treatment: 
No
Other type of more stringent treatment: 

Not provided

Other type of more stringent : 

Not provided

ID of E-PRTR facility: 

Not provided

Accidents: 
No
Remarks: 

Not provided

Forward looking aspect
Identified reason(s) for non compliance: 
Odsotnost čistilne naprave
Measure(s) to reach the compliance needed for UWWTP: 
Izgradnje nove ČN
Load entering the UWWTP at the expected date of compliance (as planned): 
2111
Organic design capacity UWWTP (as planned): 
2500
Type of treatment UWWTP (as planned): 
3NP
Date or expected date of completion of preparatory measures (planning, design, etc): 
01 December 2015
Date or expected start date for works: 
01 December 2016
Date or expected date of completion of works: 
01 December 2019
Expected date of compliance (12 months of compliant samples) : 
01 December 2020
Forecast cost investment needed for the UWWTP (as in the national plan): 
1.08
Name of EU fund planned to be used UWWTP (if any): 
CF
Amount of (planned) EU funding needed: 
0.88