OURANOPOLI

Agglomeration view on a map with some info

UWWTP : OURANOPOLI - Identifier : GR1270120548 - Status : Active - Connected - Reporting year : 2014
Region (NUTS) Code : GR127 - Region (NUTS) Name : GR127

compliance Time Line
List of all the year available for the agglomeration

2012

2014

2016

 
Compliant
 
Not compliant
 
Not relevant
 
No information
 
?


Description
Load entering UWWTP (p.e.): 
load expressed in population equivalent shall be calculated on the basis of the maximum average weekly load entering the treatment plant during the year, excluding unusual situations such as those due to heavy rain (Article 4 of the Urban Waste Water Treatment Directive 91/271/CE)
2 288
Method used to determine the load : 
Not available
Rate of entering load transported to this UWWTP by trucks (%): 
Not available
Physical Capacity (p.e.): 
2 500
Waste water treated (m3/y): 
Volume of waste water treated and partially treated in the UWWTP
Not available
Method used to determine the volume of waste water treated: 
Not available
Treatment performance: BOD5: 
Biological Oxygen Demand
Fail
Treatment performance: COD: 
Chemical Oxygen Demand
Fail
Treatment performance: TSS: 
Total Suspended Solids
Fail
Treatment performance: Total nitrogen: 
Sum of total kjeldahl nitrogen (organic, ammonia and ammonium), nitrate and nitrite
NR
Treatment performance: Total phosphorus: 
Sum of dissolved phosphorus and insoluble phosphorus
NR
Treatment performance: Other: 
e.g. e-coli
NR
Compliance: 
Not compliant
Treatment type in place: 
More stringent treatment
Treatment required: 
Secondary treatment
Treatment met: 
Yes
Performance met: 
No
In cause of failure: Bad operating/Bad design or dimensioning: 
0
In cause of failure: Bad design or dimensioning: 
0
In cause of failure: Further information on cause of failure: 
Not available
Graphical network summary
Network
Agglomerations : 1 Agglomeration : OURANOPOLI
(Generated
Network
Network
Entering :
2,288 p.e
Network
N
Network
P
Network
OZONE
Network
    Main treatment :
  • Network : Compliant
  • Network : Not compliant
  • Network : No information / Not relevant
    More stringent treatment :
    Performance :
  • Network : Pass performance
  • Network : Fail performance
  • Network : Not relevant

    Type :
  • N : Nitrogen removal
  • P : Phosphorus removal
  • UV : UV treatment
  • MICRO : Micro Filtration

    Type :
  • CHLOR : Chlorination
  • OZONE : Ozonation
  • SAND : Sand filtration
  • O : Other more stringent
    Discharge point :
  • Network : Discharge point
  • DCP(S) : Discharge point(s)
Waste Water Network Connexions
Linked agglomeration(s): 
Linked receiving area(s): 
Not available
Linked discharge point(s): 
Site information
Characteristics
 40.33000000
 23.99000000
Date of closing: 

Not provided

Explanation for closing: 

Not provided

ID of the successor: 

Not provided

Primary treatment: 
No
Secondary treatment: 
Yes
N removal: 
Yes
P removal: 
Yes
UV: 
No
Ozonation: 
Yes
Sand filtration: 
No
Chlorination: 
No
Micro filtration: 
No
Other treatment: 
No
Other type of more stringent treatment: 

Not provided

Other type of more stringent : 

Not provided

ID of E-PRTR facility: 

Not provided

Accidents: 
No
Remarks: 

Not provided

Forward looking aspect
Identified reason(s) for non compliance: 
Lack of sufficient number of samples due to financial problems and to shortage of qualified personnel
Measure(s) to reach the compliance needed for UWWTP: 
After the inspection from the relevant authorities, the necessary funds will be given for the guarantee of the satisfactory operation
Load entering the UWWTP at the expected date of compliance (as planned): 
2288
Organic design capacity UWWTP (as planned): 
2500
Type of treatment UWWTP (as planned): 
3Nm
Date or expected date of completion of preparatory measures (planning, design, etc): 
31 December 2014
Date or expected start date for works: 
31 December 2015
Date or expected date of completion of works: 
31 December 2016
Expected date of compliance (12 months of compliant samples) : 
31 December 2017
Forecast cost investment needed for the UWWTP (as in the national plan): 
100000.00
Name of EU fund planned to be used UWWTP (if any): 
Cohesion fund (CF)
Amount of (planned) EU funding needed: 
85000.00
Any relevant comment on UWWTP: 
more stingent nitrogen removal and desinfection