Beta Version : remaining inconsistencies are possible. They will be corrected during the next reporting exercise

GALATISTA

Agglomeration view on a map with some info

Agglomeration : GALATISTA - Identifier : EL12700201 - Status : Active - Reporting year : 2016
Region (NUTS) Code : EL527 - Region (NUTS) Name : EL527

compliance Time Line
List of all the year available for the agglomeration

2012

2014

2016

2018

 
Compliant
 
Not compliant
 
Not relevant
 
No information
 
?


Description
See diagram
Generated load (p.e.): 
Load generated by the agglomeration. It Includes load generated by resident and non-resident population (e.g. tourism), industrial and tertiary sectors connected to collecting system, rain under normal climatic conditions. It integrates Individual or Appropriate systems and seasonal variation.
2 515
Connected to collecting system: 
98.0 % (2,465 p.e.) based on estimated method
Individual or Appropriate Systems (IAS): 
2.0 % (50 p.e.) based on estimated method
Discharged without treatment: 
0.0 % (0 p.e.)
Methods used for calculation of the generated load: 
The method was based on permanent population data (census 2011) supplemented by seasonal population (principally on the basis of accommodation facilities) and wherever applicable industrial contribution. In some cases the above findings were verified with the aid of the number of water meters indicative of the number of households, commercial facilities etc, served and on the basis of appropriate number of people per household.
Significant changes of the generated load : 
false
Comments on significant changes: 

Not provided

Remarks: 
2% of the collecting system of the agglomeration has not been constructed and the generated sewage is treated by a system of septic tank-cesspool.
Generated Load by collection type in population equivalent
See the data table
Compliance: 
Not compliant
Connection compliance: 
Connection to "collecting system" or "Individual or appropriate system" as requested by Article 3 of the Urban Waste Water Treatment directive 91/271/EC
Compliant
2nd treatment compliance: 
Not Compliant
3rd treatment compliance: 
Not relevant
Article 6 compliance: 
Primary treatment
Not relevant
Distance to target:
The distance to target concept present the rate of waste water load that is:
  • adequately connected to a centralised urban waste water collecting system or addressed via Individual or Appropriate System (IAS)
and then when collected:
  • treated at an adequate level (secondary or more stringent treatment) as required by the directive,
  • and with the performance requirements under tables 1 or 2 of the annex I of Directive 91/271/EEC, (UWWTD).
When countries joined the EU, they have obtained a delay to implement the Directive. In such case the deadline for implementing the above (see in section characteristics) may be different, and if the above is not already implemented for the agglomeration it is identified with orange colour in the table.
Equipment Performance
Collection 0.0%
0 p.e
2nd treatment 0,0% 98,0%
0 p.e 2 465 p.e
3rd treatment - -
- -
Graphical network summary
Individual And Appropriate Systems: 50 p.e (2.0%)
Network
Network
GALATISTA
Generated load : 2,515 p.e
Collecting system :
2,465 p.e
(98.0%)
Network
Network
Load entering from:
GALATISTA
2,465 p.e (98.0%) 1
Network
N
Network
Discharge without treatment: 0 p.e (0.0%)

Network
    Main treatment :
  • Network : Compliant
  • Network : Not compliant
  • Network : No information / Not relevant
    More stringent treatment :
    Type :
  • N : Nitrogen removal
  • P : Phosphorus removal
  • Other : Other more stringent
  • UV : UV treatment

    Type :
  • OZONE : Ozonation
  • SAND : Sand filtration
  • MICRO : Micro Filtration
  • CHLOR : Chlorination
    Discharge point :
  • Network : Discharge point
  • DCP(S) : Discharge point(s)
  • 1: value based on estimated method
Waste Water Network Connexions
Linked Treatment Plant(s): 
Linked discharge points: 
Linked receiving areas: 
Not available
ID of the big city/ big discharger: 

Not provided

Linked Big city(ies): 

Not provided

Site information
Characteristics
 40.46740000
 23.27680000
Name of municipalities/communes of this agglomeration: 

Not provided

Agglomeration begin life: 
Not available
Agglomeration end life: 

-

Deadline connection compliance: 
Deadline as regards the connection to "collecting system" or "Individual or appropriate system" as requested by Article 3 of the Urban Waste Water Treatment directive 91/271/EC
12/31/2005
Deadline 2nd treatment compliance: 
Deadline as regards the secondary treatment in place and performance met as requested by Article 4 and Annex I.B of the Urban Waste Water Treatment directive 91/271/EC
12/31/2005
Deadline 3rd treatment compliance: 
when agggenerated < 10000 set to Nor Relevant
Not Relevant
Type of sewage network: 
separated/combine/separated and combine
Not available
Leaks registration: 
Is a registration system for leaks in place?
false
Maintenance plan: 
Is a maintenance plan (quality assurance) in place?
false
ID of the successor: 

Not provided

Indicate number of overflows: 
Not available
How much raw sewage has been discharged through combined sewer overflows (CSOs) in the year reported: p.e.: 

Not provided

How much raw sewage has been discharged through combined sewer overflows (CSOs) in the year reported: m3/y: 

Not provided

What are the measures based on: Acceptable number of overflows per year: 
No
What are the measures based on: Capacity in relation to dry weather flow: 
No
What are the measures based on: Dilution rates: 
No
When will the total generated load of the agglomeration be collected through collecting systems or adressed through IAS?: 

-

IAS - in situ and/ or transported to UWWTPs by trucks: How much in % of generated load of agglomeration with more stringent trea: 
0.00 %
IAS - in situ and/ or transported to UWWTPs by trucks: How much in % of generated load of agglomeration with primary treatment: 
2.00 %
IAS - in situ and/or transported to UWWTPs by trucks: How much in % of generated load of agglomeration with secondary treatment: 
0.00 %
Is best technical knowledge to limit pollution applied?: 

Not provided

Pressure test: 
No
Video inspection: 
No
Other measures: 
No
Short explanation of other measures: 

Not provided

Forward looking aspect
Identified reason(s) for non compliance: 
Upgrading of the existing UWWTP
Measure(s) foreseen to reach compliance with Article 3 (collecting systems and IAS): 
The construction project for the necessary infrastructure is under completion
Date or expected date for completion of preparatory measures for the collecting system or IAS (planning, design, procurement, c: 
31 December 2013
Start date or expected start date for works on the collecting systems or IAS: 
21 December 2014
Expected date of completion of the collecting system or IAS works: 
30 June 2017
Forecast investment cost for the collecting system or IAS (as in the national plan): 
0.00
Name of EU fund planned to be used to complete the collecting system or IAS (if any): 
Cohesion fund (CF)
Any relevant comment on collecting system or IAS: 
The UWWTP has been completed since the year 2017 and it is functional
Theorical compliance for art 5 if the Art 5.2,3 was applied: 
Theorical compliance for art 5 if the Art 5.2,3 was applied

Not provided