Umag

Agglomeration view on a map with some info

UWWTP : Umag - Identifier : HRUWWTP_0001156_001 - Status : Active - Connected - Reporting year : 2016
Region (NUTS) Code : HR036 - Region (NUTS) Name : Istarska županija

compliance Time Line
List of all the year available for the agglomeration

2012

2014

2016

 
Compliant
 
Not compliant
 
Not relevant
 
No information
 
?


Description
Load entering UWWTP (p.e.): 
load expressed in population equivalent shall be calculated on the basis of the maximum average weekly load entering the treatment plant during the year, excluding unusual situations such as those due to heavy rain (Article 4 of the Urban Waste Water Treatment Directive 91/271/CE)
Not available
Method used to determine the load : 
Not available
Rate of entering load transported to this UWWTP by trucks (%): 
Not available
Physical Capacity (p.e.): 
20 000
Waste water treated (m3/y): 
Volume of waste water treated and partially treated in the UWWTP
Not available
Method used to determine the volume of waste water treated: 
Not available
Treatment performance: BOD5: 
Biological Oxygen Demand
NA
Treatment performance: COD: 
Chemical Oxygen Demand
NA
Treatment performance: TSS: 
Total Suspended Solids
NA
Treatment performance: Total nitrogen: 
Sum of total kjeldahl nitrogen (organic, ammonia and ammonium), nitrate and nitrite
NA
Treatment performance: Total phosphorus: 
Sum of dissolved phosphorus and insoluble phosphorus
NA
Treatment performance: Other: 
e.g. e-coli
NA
Compliance: 
PD
Treatment type in place: 
Primary treatment
Treatment required: 
Treatment met: 
Not Calculable
Performance met: 
Not Calculable
In cause of failure: Bad operating/Bad design or dimensioning: 
Not available
In cause of failure: Bad design or dimensioning: 
Not available
In cause of failure: Further information on cause of failure: 
Not available
Graphical network summary
Network
Agglomerations : 1 Agglomeration : Umag
(Generated
Network
Network
Entering :
0 p.e
Network
    Main treatment :
  • Network : Compliant
  • Network : Not compliant
  • Network : No information / Not relevant
    More stringent treatment :
    Performance :
  • Network : Pass performance
  • Network : Fail performance
  • Network : Not relevant

    Type :
  • N : Nitrogen removal
  • P : Phosphorus removal
  • UV : UV treatment
  • MICRO : Micro Filtration

    Type :
  • CHLOR : Chlorination
  • OZONE : Ozonation
  • SAND : Sand filtration
  • O : Other more stringent
    Discharge point :
  • Network : Discharge point
  • DCP(S) : Discharge point(s)
Waste Water Network Connexions
Linked agglomeration(s): 
Linked receiving area(s): 
Linked discharge point(s): 
Site information
Characteristics
 45.42500000
 13.52560000
Date of closing: 

Not provided

Explanation for closing: 

Not provided

ID of the successor: 

Not provided

Primary treatment: 
Yes
Secondary treatment: 
No
N removal: 
No
P removal: 
No
UV: 
No
Ozonation: 
No
Sand filtration: 
No
Chlorination: 
No
Micro filtration: 
No
Other treatment: 
No
Other type of more stringent treatment: 

Not provided

Other type of more stringent : 

Not provided

ID of E-PRTR facility: 

Not provided

Accidents: 
Not available
Remarks: 
UWWTP is marked as „primary treatment“ although it includes treatment processes of lower level than primary; nevertheless, treatment includes at least removal of larger suspended solids and floating particles, including removal of oil and grease and/or discharge of treated water with long submerged marine outlets, where the use of such treatment in certain areas enables reaching of the water quality goals and which represents appropriate treatment in such areas.
Forward looking aspect
Identified reason(s) for non compliance: 
not relevant
Measure(s) to reach the compliance needed for UWWTP: 
building of the new WWTP, reconstruction and/or upgrade of the existing WWTP to ensure required level of treatment and capacity
Load entering the UWWTP at the expected date of compliance (as planned): 
57013
Organic design capacity UWWTP (as planned): 
59000
Type of treatment UWWTP (as planned): 
3NP
Date or expected date of completion of preparatory measures (planning, design, etc): 
31 January 2019
Date or expected start date for works: 
31 March 2020
Date or expected date of completion of works: 
31 October 2023
Expected date of compliance (12 months of compliant samples) : 
31 October 2024
Forecast cost investment needed for the UWWTP (as in the national plan): 
14.77
Name of EU fund planned to be used UWWTP (if any): 
CF
Amount of (planned) EU funding needed: 
10.51