Beta Version : remaining inconsistencies are possible. They will be corrected during the next reporting exercise

Kanalizacia Branipole

Agglomeration view on a map with some info

UWWTP : Kanalizacia Branipole - Identifier : BGCO06077_00_01 - Status : Inactive - Connected - Reporting year : 2016
Region (NUTS) Code : BG421 - Region (NUTS) Name : Пловдив (Plovdiv)

compliance Time Line
List of all the year available for the agglomeration

2012

2014

2016

2018

 
Compliant
 
Not compliant
 
Not relevant
 
No information
 
?


Description
Load entering UWWTP (p.e.): 
load expressed in population equivalent shall be calculated on the basis of the maximum average weekly load entering the treatment plant during the year, excluding unusual situations such as those due to heavy rain (Article 4 of the Urban Waste Water Treatment Directive 91/271/CE)
Not available
Method used to determine the load : 
Not available
Rate of entering load transported to this UWWTP by trucks (%): 
Not available
Physical Capacity (p.e.): 
Not available
Waste water treated (m3/y): 
Volume of waste water treated and partially treated in the UWWTP
Not available
Method used to determine the volume of waste water treated: 
Not available
Treatment performance: BOD5: 
Biological Oxygen Demand
Not available
Treatment performance: COD: 
Chemical Oxygen Demand
Not available
Treatment performance: TSS: 
Total Suspended Solids
Not available
Treatment performance: Total nitrogen: 
Sum of total kjeldahl nitrogen (organic, ammonia and ammonium), nitrate and nitrite
Not available
Treatment performance: Total phosphorus: 
Sum of dissolved phosphorus and insoluble phosphorus
Not available
Treatment performance: Other: 
e.g. e-coli
Not available
Compliance: 
Not relevant
Treatment type in place: 
No information
Treatment required: 
Treatment met: 
Not Calculable
Performance met: 
Not Calculable
In cause of failure: Bad operating/Bad design or dimensioning: 
Not available
In cause of failure: Bad design or dimensioning: 
Not available
In cause of failure: Further information on cause of failure: 
Not available
Graphical network summary
Network
Agglomerations : 1 Agglomeration : Branipole
(Generated
Network
Network
Entering :
0 p.e
Network
    Main treatment :
  • Network : Compliant
  • Network : Not compliant
  • Network : No information / Not relevant
    More stringent treatment :
    Performance :
  • Network : Pass performance
  • Network : Fail performance
  • Network : Not relevant

    Type :
  • N : Nitrogen removal
  • P : Phosphorus removal
  • UV : UV treatment
  • MICRO : Micro Filtration

    Type :
  • CHLOR : Chlorination
  • OZONE : Ozonation
  • SAND : Sand filtration
  • O : Other more stringent
    Discharge point :
  • Network : Discharge point
  • DCP(S) : Discharge point(s)
Waste Water Network Connexions
Linked agglomeration(s): 
Linked receiving area(s): 
Linked discharge point(s): 
Site information
Characteristics
 42.08155200
 24.75695800
Date of closing: 

Not provided

Explanation for closing: 

Not provided

ID of the successor: 

Not provided

Primary treatment: 
Not available
Secondary treatment: 
Not available
N removal: 
Not available
P removal: 
Not available
UV: 
Not available
Ozonation: 
Not available
Sand filtration: 
Not available
Chlorination: 
Not available
Micro filtration: 
Not available
Other treatment: 
Not available
Other type of more stringent treatment: 

Not provided

Other type of more stringent : 

Not provided

ID of E-PRTR facility: 

Not provided

Accidents: 
Not available
Remarks: 
Connected to UWWTP
Forward looking aspect
Identified reason(s) for non compliance: 
absence ot WWTP
Measure(s) to reach the compliance needed for UWWTP: 
construction of WWTP
Load entering the UWWTP at the expected date of compliance (as planned): 
2608
Organic design capacity UWWTP (as planned): 
2608
Type of treatment UWWTP (as planned): 
2
Date or expected date of completion of preparatory measures (planning, design, etc): 
31 December 2024
Date or expected start date for works: 
31 December 2025
Date or expected date of completion of works: 
31 December 2029
Expected date of compliance (12 months of compliant samples) : 
31 December 2030
Forecast cost investment needed for the UWWTP (as in the national plan): 
2.06
Any relevant comment on UWWTP: 
The deadline is according to the Multiannual Financial Framework 2021-2027